Saturday 28 June 2014

Permanent Grout filled Flat Jacks

Tricky flat jacking operation completed successfully by Hydra-Capsule within programme and budget (www.hydra-capsule.com) using or special purpose-built high pressure injection systems.

The works consisted of 21 off. Transfusion flat jacks with a capacity of 40 tons each, 840 ton in total..



Therefore all the jacks were interlinked and synchronously loaded to the specified defined loads, displacements/deflection and limits.

Once competed, each jack (which were jacked/lifted/preloaded with hydraulic fluid) was individually transfused using a double-release valve arrangement, to inject grout and release temporary fluid until the flat jack was fully transferred. Find detailed explanation of the above flat jacking operations at http://www.hydra-capsule.com/flat-jacks . 




The key element of the operation, is the jack can be accurately monitoring and maintain the original preload and movement with the structural steelwork being subjected to additional loads and/or further stresses. 

Monday 9 June 2014

Hydraulic Jacking and Structural Support Systems






 The St Katharine Docks, in the London Borough of Tower Hamlets, were one of the commercial docks serving London, on the north side of the river Thames just east (downstream) of the Tower of London and Tower Bridge. They were part of the Port of London, in the area now known as the Docklands, and are now a popular housing and leisure complex.

Multi products and services provided and completed by Hydra Capsule at the Quayside Redevelopment Project.

The works involved a mixture of products and services to support the complex remedial works throughout the site.

Hydra Capsule used permanent flat jacks to pre-loaded and pre-stressed numerous areas of steelworks, to assist with structural strengthening and limiting displacement and deflection of critical areas within the structure.

In addition, Hydra Capsule also supplied temporary propping support systems at critical and high-risk areas of the project. Installing supports up to 400 tonnes (Mega-Prop) at particular location(s). With the inclusion of long-stroke (+150mm) hydraulic jacks to synchronously pre-load the supports.

All works were carried out using high-accurate movement LVDTs (+/- 0.02mm) and load sensors (+/- 1 kN) to meet the critical loading and displacement criteria provided by the structural consultant engineers. The complete system was connected to Hydra-Capsule ‘purpose built’ read-out monitoring control unit. Which allows all information to be provided in “live” real-time data display.

Once these works were completed, Hydra Capsule also provided grout injection systems to permanently transfuse flat jacks and carried out concrete strengthening and repairs at badly damaged concrete areas.